Various alerts are sent as tasks are assigned and statuses changed however for tasks within a process there are no notifications sent to a user to alert them that a task that was previously assigned to them has now become active and so is now waiting on them.

The task may have been assigned to them weeks earlier for example but today the previous task was completed. Alerts are sent from the completion but there is no specific alert sent to the user who is "next in line" to tell them that their task that had been suspended for weeks is now Active and waiting on them.

Therefore a user who uses Teamwork only rarely may not be aware that a process has reached a stage where it is now waiting on them to complete a task for the process to continue.

asked Jul 11 '11 at 03:37

daveo's gravatar image

daveo
764

closed Jul 11 '11 at 09:08

Silvia%20Chelazzi's gravatar image

Silvia Chelazzi ♦♦
408519

The question has been closed for the following reason "Duplicate Question see "Notification when task status changes from suspended to active not being sent"" by Silvia Chelazzi Jul 11 '11 at 09:08

Follow this question

By Email:

Once you sign in you will be able to subscribe for any updates here

By RSS:

Answers

Answers and Comments

Tags:

×60
×18
×15

Asked: Jul 11 '11 at 03:37

Seen: 163 times

Last updated: Jul 11 '11 at 09:08

| Teamwork faq | about | contact us | Teamwork blog | Teamwork documentation | feedback always welcome